PM-DHARA to strengthen Intra-State Transmission System

|

PM-DHARA to strengthen Intra-State Transmission System

Schemes
PM-DHARA to strengthen Intra-State Transmission System

The Union Cabinet has approved the ₹1.86 lakh crore PM-DHARA scheme. The scheme strengthens India’s Intra-State Transmission System (InSTS) and provides for Battery Energy Storage Systems deployment to support renewable-energy evacuation and grid flexibility.

PM-DHARA Scheme:

Dimension Key Details
Full Form PM-DHARA stands for PM-Developing Harmonized and Accelerated Renewable-energy Access.
Renewable Energy Evacuation Capacity The scheme provides for enabling evacuation of up to 135 GW of renewable energy across States and Union Territories.
Battery Energy Storage Systems (BESS) The scheme provides for deployment of 50 GWh of BESS at generator ends or other locations crucial for grid flexibility.
Implementation Timeline The scheme is targeted for implementation by FY 2032-33.
Financial Outlay The project outlay comprises ₹1,36,378 crore for development of InSTS under Green Energy Corridor Phase-III (GEC-III) and ₹50,000 crore for 50 GWh of BESS.
Central Financial Support The scheme involves total Central Financial Support of ₹54,082 crore.
Implementation Mode All Greenfield projects under the InSTS component are implemented through Tariff Based Competitive Bidding (TBCB) mode, and Brownfield upgradation and network strengthening works are executed under Cost Plus Basis (CPB).
Implementing Agency and Participation Model The State Transmission Utilities are the overall implementing agency, and Transmission Service Providers participate under TBCB on a Build-Own-Operate-Maintain (BOOM) model.
Did you find this informative?

Attempt Possible Qs

Q 1 / 3

With reference to the PM-DHARA scheme, consider the following statements:

1. It provides for enabling evacuation of up to 135 GW of renewable energy across States and Union Territories.
2. It provides for deployment of 50 GWh of Battery Energy Storage Systems (BESS) at generator ends or other locations crucial for grid flexibility.
3. All Greenfield projects under the InSTS component are implemented through Cost Plus Basis (CPB) mode.

Which of the statements given above are correct?

Show answerHide answer

Answer: A. 1 and 2 only